‘$4bn needed to transform power transmission infrastructure’

The Nepal Electricity Authority (NEA) has estimated that the country needs to invest as much as $4bn by 2030 to transform the existing transmission infrastructure. In a presentation at a program last week, NEA Managing Director Kul Man Ghising said an investment of $3.95bn will be required to complete the NEA’s plan of transforming the existing transmission infrastructure which has remained poor and unreliable. According to him, it will require $2.51bn for the planned and ongoing transmission line projects within the Kathmandu Valley and outside. An additional $1.44bn will be required for constructing the substations. NEA is currently developing and has planned to develop 400kV, 220kV, 132kV, and 66kV transmission lines and substations. Even though load shedding in the country officially ended in May 2019, the reliability of the power supply has been a major concern for industrial and general consumers. The NEA leadership has time and again insisted that the next major focus would be to improve the transmission and distribution infrastructure of power supply. NEA has been forced to cut power industries based in the Birgunj area because of failure to supply power there due to poor transmission infrastructure. Nepal has been importing electricity from India during the dry season but it has not been able to deliver the imported power from India to Birgunj where industries are facing daily power cuts. One of the main reasons behind the failure to deliver the imported power to the area is poor transmission infrastructure. “Existing transmission line cannot carry much power,” said an NEA official. “So, we have failed to deliver power from Dhalkebar to Birgunj.” Nepal has been importing power through the 400kV Dhalkebar-Muzaffarpur Cross Border Transmission Line from the Indian market. While domestic transmission infrastructure has remained poor, the cross-border transmission infrastructure between Nepal and India is also not efficient. For example, the 132kV Raxaul-Parwanipur Cross Border Transmission Line can transmit only 80MW of electricity. The 33kV Raxual-Birgunj Transmission Line Project can carry only 12MW electricity. “We have requested the Bihar State government for the supply of additional 90MW of electricity through improvement in cross border power lines,” said the NEA official. Considering the poor state of cross-border power lines, Nepal and India agreed to upgrade these transmission lines. There are a dozen cross-border power lines between Nepal and India. Except for Dhalkebar-Muzaffarpur, the capacity of other power lines range between 33kV to 132kV, according to the NEA. So improving domestic and cross-border electricity lines between Nepal and India has emerged as a major priority for the government-owned power utility to ensure the reliability of the power supply. NEA officials say improving the quality of power supply is important to promote the use of electric vehicles and electric cooktops in the country as well.

Babai Irrigation Project: 37 years and construction still slow

It's been over three and half decades since the government began construction of the Babai Irrigation Project, one of the national pride projects, which has achieved only 65 percent of the physical progress so far. The development of the Babai Irrigation Project commenced in the fiscal year 1988/89 and the completion deadline has been set to FY 2025/26. Given the current pace of the construction, it is unlikely that the project would be completed in the next three and half years. The project has to complete 35.76 percent of the remaining work by that time to meet the construction deadline. However, project officials say that there is a challenge in completing the remaining work during that period. The physical progress of the project in mid-July was 62.23 percent. And, only 2.01 percent of additional physical progress has been achieved in the first six months of this fiscal year. The project officials admit this progress is not satisfactory. In order to complete the construction of the project within the specified deadline, physical progress should be made at the rate of 3 percent quarterly, 6 percent semi-annually and 12 percent annually. However, the report of the project has confirmed that work has not been done accordingly. Now, project officials say there is no option but to extend the deadline. Although the construction started in FY 1988/89, the funding was inadequate at the beginning. Later, in FY 2012/13, Babai Irrigation was given the status of a 'national pride project', and after this, a larger budget was allocated for the project. However, the construction of the project was again affected by the Covid-19 pandemic and the delay by the contractor. Ramakrishna Ghorasaini, Information Officer of the project, said that it is difficult to complete the construction within the stipulated timeframe. "While the construction of the project was going smoothly, the pandemic stalled the works for almost two years," he said, adding, "Last year, the contractors did not work citing the rise in the price of construction materials." The project was launched by the government with the aim of providing irrigation facilities to around 36,000 hectares of arable land in the Bardia district. The total cost of the project is estimated at Rs18.96bn, which will be invested by the government. So far, Rs11.63bn has been spent on the project. Initially, the estimated cost of the project was Rs2bn which has gone up with the delay in the construction with each passing year.

Fiscal deficit grows wider as revenue shortfall continues

With the government struggling to strike a balance between income and expenditure, the federal budget is currently in deficit which is increasing every successive month. The statistics of the Financial Comptroller General Office (FCGO) show the federal budget is in deficit by Rs 153.61 billion till March 5. The government revenue till the first week of March stood at Rs 594.91 billion whereas expenditure has reached Rs 748.52 billion. With the government failing to collect enough revenue while expenditures, particularly the recurrent expenditure, are rising fast, the fiscal imbalance is growing alarmingly. According to FCGO, the fiscal deficit began by the end of Ashoj (mid-September to mid-October) with the government failing to collect revenue as per target while recurrent expenditure, especially continue to increase. The government has targeted to collect Rs 1,244.75 billion in revenue in the current fiscal year. However, even after almost eight months, only 44.58 percent of the target has been achieved. With fiscal deficit looming, the government on February 12, announced a cut in its annual budget by a whopping 13.59 percent, the largest cut in recent times, after realizing that it would not be able to raise the required resources from all the most sources—particularly revenue and foreign aid. The revised budgetary allocation now amounts to Rs 1,549.99 billion from the original size of Rs 1,793.83 billion. The government’s revenue collection suffered mainly due to the prolonged import restrictions on a number of products including vehicles, alcohol, and expensive mobiles as well as the provision of cash margin in imports. The restrictions were first imposed in April 2022 for the import of 10 types of products. The number of restricted products was later reduced gradually but the ban on vehicles, alcohols, and expensive mobile sets continued till mid-December last year when the embargo was eventually lifted. The Nepal Rastra Bank made it mandatory to deposit a cash margin of up to 100 percent for opening letters of credit for the import of a number of products which also hit import-based revenue. Import covers around 50 percent of Nepal’s total revenue, according to the Department of Customs. Though these measures were taken to address the external sector vulnerability amid the ballooning balance of payment deficit and depleting foreign exchange reserves, the restrictive steps created a new problem of shortfall of resources for the government. The shortfall in revenue was also aggravated by increased compulsory liability by the previous government led by Sher Bahadur Deuba by increasing salaries for public officials and increasing the beneficiaries of social security allowances. This prompted the government to take harsh measures of budget cuts. A reprioritization of projects which have not been implemented even after getting a resource guarantee from the finance ministry, surrender of the budget which cannot be spent in the current fiscal year, and abandoning any proposal that creates new liabilities are other austerity measures announced by the Finance Ministry.

Gold price drops by Rs 300 per tola on Tuesday

The price of gold has dropped by Rs 300 per tola in the domestic market on Tuesday. According to the Federation of Nepal Gold and Silver Dealers’ Association, the yellow bullion is being traded at Rs 102, 500 per tola today. The yellow metal was traded at Rs 102, 800 per tola on Monday. Meanwhile, tejabi gold is being traded at Rs 102, 000 per tola. Similarly, the price of silver has dropped by Rs 10 and is being traded at Rs 1,265 per tola today.